Lake Stevens, Washington, has its first look at the school that will replace Glenwood Elementary. The Lake Stevens School District has released design renderings of the new $70.7 million building, The Daily Herald reported earlier this month.
The new school will be three stories tall. Construction is planned to start in June 2027, and the building is scheduled to be finished for the 2028-29 school year.
What is being built
The new Glenwood will have 26 learning spaces with room for more than 650 students, according to planning documents cited by the Herald. Glenwood enrolls about 640 students now, and the district is adding 50 to 100 students a year.
Get today’s Lake Stevens report for your trade, free →
The school sits next to a protected wetland, so the new building has to stay within the footprint of the existing one, the Herald reported. That is the reason for building up. Site plans show a bus loop, a separate family drop-off, a turf field and a play area in front of the building. Classrooms will look out on the wetland, and an outdoor classroom is planned beside it.
The district's Glenwood project page says the campus will also get a secure perimeter fence, which the renderings do not show.
Why a new building
Glenwood was built in 1992. "The original plan called for modernizing and expanding the existing school," the district's project page says. The district says the open-concept classrooms, small library, aging systems and tight site led it to replace the school instead. The page says the school board approved building new, in place of a remodel, in April 2026, and that the project still qualifies for state construction money.
The money
Lake Stevens voters passed a capital improvement bond in February 2025 to pay for the work. The state is also providing $12.3 million toward Glenwood.
Across the whole bond program, state money stretches the local dollars. "So, the $314 million that the community has contributed will actually get us more than $400 million," Robb Stanton, the district's executive director of school planning and construction, told the Herald.
The same bond is paying for a new elementary school that has not been named yet, a new Skyline Elementary, a learning center for secondary students, an expansion of Lake Stevens Middle School and a gymnasium at Hillcrest Elementary.
What's next
The project is in the permitting phase. The district sent its ecological permitting paperwork to the state Department of Ecology on Oct. 27, the Herald reported.
Glenwood students and staff will spend the school year that starts in fall 2027 in that not-yet-named new elementary school while their campus is rebuilt. The district's page says the new Glenwood is expected to open in fall 2028.
Sources
- Lake Stevens unveils first renderings of Glenwood Elementary School, The Daily Herald
- New Glenwood Elementary project page, Lake Stevens School District
More from Morningline Research
- Northwestern's Arkes Pavilion gets a $10 million permit for its 13th floor
- The J's indoor water park gets a $10.3 million permit in Overland Park
- Dana-Farber gets a $22.6 million permit for a nuclear medicine suite at 44 Binney St.
- Carrier's Fort Worth chiller plant gets a $47 million permit to fit out Alliance Westport 12