Fort Worth, Texas has issued a $47 million building permit to turn a brand-new warehouse at 1501 Distribution Dr. into a factory. The permit, dated Nov. 8, covers about 600,000 square feet of the 1.2 million-square-foot building and lays out room for "three production lines."
The building is Alliance Westport 12, in the AllianceTexas district on the city's far north side. It's the site Carrier chose for a new plant that will build commercial chillers, the big cooling units that keep data centers, hospitals and campuses running.
From empty shell to factory floor in one year
The first permit at the address came Feb. 1. It was for a "1,219,034 square feet shell warehouse," with a reported value of $48 million. The state's construction project registry lists the same building as a "cold dark shell" with no tenant assigned, an estimated cost of $47,682,691 and a finish date of April 2027.
Get today’s Fort Worth report for your trade, free →
So the walls weren't even finished before a user turned up.
The Nov. 8 permit reads like a factory plan. It calls for selective demolition and upgrades to roughly half the building, new office space, mezzanines, stairs and an elevator. It adds new utility and support buildings, changes to the tilt-wall panels, structural and mechanical upgrades, and a refrigerant storage canopy. Its stated purpose is infrastructure "to support three production lines."
The permit doesn't name the company. Bisnow tied the building to Carrier, and its reporting matched the permit's scope: about half the building, three lines for air- and water-cooled chillers, plus office space and a new elevator, CRE Daily reported.
Permit values are estimates filed with the city, not contract amounts. The two permits are for different work and both stand on their own.
How Fort Worth landed it
Fort Worth wasn't the only city in the running. It competed with three other states, Virginia and Alabama among them, Community Impact reported in September. The city's economic development staff pitched the project to the council at an Aug. 25 work session.
On Sept. 15 the council created a tax abatement reinvestment zone for the site and nominated the project for a Texas Enterprise Zone grant worth an estimated $2.5 million. The deal is a seven-year, 60% abatement valued at $10.9 million. In return, Carrier has to invest at least $433.8 million, about $36 million of it in the building and $397.8 million in equipment, and add 495 full-time jobs averaging at least $75,000 a year by the end of 2029, according to Community Impact.
The city expects about $7.3 million in net new taxes and $261.7 million in added payroll over the seven years. It would be the largest single-facility investment in Carrier's history, assistant economic development director Brianna Brown told the council, according to Community Impact.
Carrier goes bigger
Then on Oct. 22 Carrier made its own announcement, and the numbers were larger than the city's minimums. The Florida company said it will spend more than $600 million over three years on a manufacturing and engineering center of more than 1 million square feet, with about 1,500 jobs. Operations are expected to start in 2027.
The center will add engineering labs alongside production, and Carrier plans to work with local schools and colleges on training, the release said. Chairman and CEO David Gitlin said the plant is about "increasing capacity for critical technologies," Facilities Dive reported. Fort Worth Mayor Mattie Parker called it "the latest example of the momentum we're building."
Demand is the reason. Carrier pointed to "record backlog levels driven by strong demand across data centers," along with health care, education and industrial customers, Facilities Dive reported. A company spokesperson told the outlet the total investment runs above the city's required minimums.
The plant fits a larger Carrier plan. In 2025 the company committed $1 billion to U.S. manufacturing, expected to create 4,000 jobs, Community Impact reported.
A neighborhood of factories
Westport 12 sits next to Wistron and Walmart, according to Community Impact. It's one of several 1.2 million-square-foot buildings going up in this corner of Alliance. Alliance Westport 16, at Mobility Way and Intermodal Parkway, is due by July 2027.

The city's deal sets Dec. 31, 2028 as the deadline for the minimum investment. Carrier expects the Distribution Drive plant to be running in 2027.
How we count
Permits come from the City of Fort Worth's building permit records for 1501 Distribution Dr., issued February through November 2026. Values are the valuations reported on the permits, not contract amounts. Company names come from the news coverage and company announcement linked here.
See Fort Worth's latest permit numbers, updated weekly.
Sources
- City of Fort Worth building permits PB26-01436 and PB26-14939.
- Texas Department of Licensing and Regulation, project registration "Hillwood Alliance - Westport 12" (TABS2026011387): tdlr.texas.gov
- Community Impact (Cody Thorn), on Fort Worth's incentive for the Carrier plant (Sept. 18, 2026; updated Oct. 16): communityimpact.com
- Carrier, news release on its Fort Worth manufacturing and engineering center (Oct. 22, 2026): carrier.com
- Facilities Dive (Jeff Kinney), on Carrier's Fort Worth plant (Nov. 3, 2026): facilitiesdive.com
- CRE Daily, summarizing Bisnow's report on the Westport 12 plans (Oct. 23, 2026): credaily.com
- Community Impact, on Alliance Westport 16 (July 1, 2026): communityimpact.com
- Photo: Designism, aerial photo of Fort Worth Alliance Airport, CC0, via Wikimedia Commons: commons.wikimedia.org
More from Morningline Research
More numbers: Fort Worth, TX building permit activity, updated weekly.
- Fort Worth issues a second $327 million permit at ACS's Hicks Field data center campus
- Fort Worth issues $57.2 million permit for a new J.P. Elder Middle School
- West Fort Worth Data Center Files $286.6 million Fit-Out for Its First Building
- Northwestern's Arkes Pavilion gets a $10 million permit for its 13th floor