Hawaii County issued two building permits on November 16 for the Pāhala Wastewater Treatment Plant at 96-3303 Maile St., in the old sugar town on the Big Island's Kaʻū coast. One covers a new 7,870-square-foot canopy building to hold the plant's wastewater equipment and tanks, at a reported value of $17 million. The other, filed as county job WW-4810, is the plant's new control building, at $10.5 million.
The plant is the piece Pāhala has been waiting on since the town's big cesspools were ordered closed nine years ago.
Nine years from order to permit
Pāhala has never had a sewer plant. Its large cesspools were built by C. Brewer, the sugar company that ran the plantation there, according to Spectrum News. The company asked the county for help closing them in 2003, and the county took ownership in 2010, Big Island Video News reported.
Get today’s Hawaii County report for your trade, free →
Federal rules from 2000 called for large cesspools like these to shut down, the Tribune-Herald reported. The county signed an order with the U.S. Environmental Protection Agency on June 22, 2017, committing to close the ones in Pāhala and nearby Nāʻālehu and replace them with treatment systems approved by the state health department, according to the EPA's case page. The order was revised in August 2022.
The November permits are the plant itself. The canopy permit calls for "wastewater equipment and tanks" under the new roof, and notes that the control building and a fire protection tank are permitted separately.
The pipes went in first

Work on the other half of the system started last year. On July 7, 2025, crews began a $30.9 million contract for the collection system: new sewer and water lines, lateral connections and repaving, according to Big Island Video News. The Hawaii Tribune-Herald reported the same start date.
That contract runs laterals to 109 properties now served by the large cesspools. Another 65 parcels will be able to hook up once the lines are in, Spectrum reported. The county put the treatment plant out to bid on June 30, 2025, a week before the pipe work began.
When the plant is running, the wastewater from those lines will be sent to it, the outlets reported.
What comes after Pāhala
A revised order the EPA proposed on August 10 sets Jan. 31, 2029 as the date for closing Pāhala's two large cesspools, according to the agency's case page. The same proposal sets Dec. 31, 2032 for the three in Nāʻālehu, the other town under the order. It was still listed as a proposal when we checked.
The rest of the state has the same job ahead on a bigger scale. Hawaii's Act 125, passed in 2017, requires every cesspool in the state to be upgraded, converted or connected before January 1, 2050, according to the session law.
The values above are reported permit values filed with the county, not contract amounts.
See the latest Hawaii County permit numbers, updated weekly.
Sources
- Spectrum News Hawaii, "Pāhala wastewater system" (July 3, 2025): spectrumlocalnews.com
- Big Island Video News, "Pāhala wastewater collection system construction starts Monday, July 7" (July 5, 2025): bigislandvideonews.com
- Hawaii Tribune-Herald, "... wastewater project kicks off in Pahala to shut down aging cesspools by 2027" (Aug. 11, 2025): hawaiitribune-herald.com
- U.S. EPA, "SDWA-UIC-AOC-2017-0002: Administrative Order on Consent with the County of Hawaii; Closure of Cesspools in Pāhala and Nāʻālehu": epa.gov
- Hawaii State Legislature, Act 125, Session Laws of Hawaii 2017: data.capitol.hawaii.gov
- County of Hawaiʻi building permits PW.B2025-002351 and PW.B2025-002352.
- Photo: Ichabod, Public domain, via Wikimedia Commons: commons.wikimedia.org