Bee Cave City Council Approves Plan for Nine Box Culverts at Great Divide Drive Low Water Crossing

Bee Cave, Texas, City Council approved an engineering report for the Great Divide Drive low water crossing that calls for nine box culverts, a project of about $1.16 million that serves the only road into the Homestead neighborhood.

By Morningline Research · November 16, 2026
Bee Cave City Council Approves Plan for Nine Box Culverts at Great Divide Drive Low Water Crossing
Graphic: Morningline Research

A long-running drainage project in Bee Cave, Texas, has a design. City Council approved an engineering report for the low water crossing on Great Divide Drive, Community Impact reported last week. The plan calls for nine bridge-class box culverts in place of the pipes there now.

The item was on the council's regular meeting agenda for Tuesday, November 10, listed as a presentation from the city's engineering firm on the Great Divide Low Water Crossing Improvement Project.

Why the crossing matters

Great Divide Drive is the only way in and out of the Homestead neighborhood in this part of Travis County. When the crossing floods, residents and first responders have trouble getting through.

Get today’s Bee Cave report for your trade, free →

The current crossing is three pipes that can carry about 60 cubic feet of water per second. A two-year rain event, like the storm that hit the city in May 2019, moves about 2,800 cubic feet per second, according to the report.

What changed from the bridge plan

The city has been working on this crossing for years. In 2023 the engineering firm brought council two options: a 200-foot bridge or eight culverts. Mayor Kara King moved to approve the bridge, but the motion failed over concerns about the effect on neighboring properties. No motion was made on the culvert option.

The new design keeps the road as a low water crossing instead of raising it onto a bridge. The engineers told council the design keeps the profile of the existing road.

What the new design does

With nine box culverts, the crossing could handle a two-year storm, according to city documents cited by Community Impact. The engineering firm gave council two measures:

"I feel confident that this gives us the best solution without impacting the neighbors," King said, according to Community Impact. She called the proposal a significant improvement over what is there now.

Cost and schedule

The total cost, including construction, right-of-way acquisition and engineering, is about $1.16 million, per city documents. The whole project is expected to take two years, with construction lasting six months.

That schedule leaves most of the two years for final design and right-of-way before a contractor is on site. The report did not give a bid date or a construction start date.

Want to wake up knowing what’s being built near you?

Tell us what you do and where, and we’ll send you a free sample report.

Your report comes from dave@morninglineleads.com, so please check your spam or junk folder if you don’t see it. Free, no card, no obligation. We work with one company per trade in each area, so if yours is taken, we’ll let you know.

Sources

More from Morningline Research