A long-running drainage project in Bee Cave, Texas, has a design. City Council approved an engineering report for the low water crossing on Great Divide Drive, Community Impact reported last week. The plan calls for nine bridge-class box culverts in place of the pipes there now.
The item was on the council's regular meeting agenda for Tuesday, November 10, listed as a presentation from the city's engineering firm on the Great Divide Low Water Crossing Improvement Project.
Why the crossing matters
Great Divide Drive is the only way in and out of the Homestead neighborhood in this part of Travis County. When the crossing floods, residents and first responders have trouble getting through.
Get today’s Bee Cave report for your trade, free →
The current crossing is three pipes that can carry about 60 cubic feet of water per second. A two-year rain event, like the storm that hit the city in May 2019, moves about 2,800 cubic feet per second, according to the report.
What changed from the bridge plan
The city has been working on this crossing for years. In 2023 the engineering firm brought council two options: a 200-foot bridge or eight culverts. Mayor Kara King moved to approve the bridge, but the motion failed over concerns about the effect on neighboring properties. No motion was made on the culvert option.
The new design keeps the road as a low water crossing instead of raising it onto a bridge. The engineers told council the design keeps the profile of the existing road.
What the new design does
With nine box culverts, the crossing could handle a two-year storm, according to city documents cited by Community Impact. The engineering firm gave council two measures:
- Time before water rises over the road in a two-year storm: 25 minutes today, 55 minutes with the new design.
- Time the road stays under water in that storm: 13 hours today, three hours with the new design.
"I feel confident that this gives us the best solution without impacting the neighbors," King said, according to Community Impact. She called the proposal a significant improvement over what is there now.
Cost and schedule
The total cost, including construction, right-of-way acquisition and engineering, is about $1.16 million, per city documents. The whole project is expected to take two years, with construction lasting six months.
That schedule leaves most of the two years for final design and right-of-way before a contractor is on site. The report did not give a bid date or a construction start date.
Sources
- Bee Cave moves forward with Great Divide Drive low water crossing project, Community Impact
- Bee Cave City Council regular meeting agenda, Nov. 10, City of Bee Cave
More from Morningline Research
- Northwestern's Arkes Pavilion gets a $10 million permit for its 13th floor
- The J's indoor water park gets a $10.3 million permit in Overland Park
- Dana-Farber gets a $22.6 million permit for a nuclear medicine suite at 44 Binney St.
- Carrier's Fort Worth chiller plant gets a $47 million permit to fit out Alliance Westport 12