The Spring Hill Board of Mayor and Aldermen in Spring Hill, Tennessee, has approved an $8.17 million contract to rebuild the intersection of Port Royal Road and Buckner Lane, Williamson Source reported. Construction is expected to begin next spring.
The board passed Resolution 26-234 last week. The city lists the exact contract at $8,173,903.81, nearly 10% under the project's $9 million budget.
What's being built
According to the city's project page, the work will:
Get today’s Spring Hill report for your trade, free →
- realign the intersection
- widen the roads
- replace the bridge on the west side
- add dedicated lanes for left turns and right turns, instead of the single lane now shared by turning and through traffic
- smooth out the hard turns with a more curved transition
- add sidewalks and pedestrian crossings
Timeline
Work will begin in spring 2027 and is expected to take about 12 months, the city said. The city plans to post periodic updates on the project page during construction.
Under budget
The approved price came in nearly 10% below the $9 million the city had budgeted, Williamson Source reported.
The city described the goal of the new layout plainly: it will "eliminate hard turn movements at the intersection and allow for a more curved transition." The new bridge on the west side and the added turn lanes are the largest pieces of the job.
Spring Hill sits on the line between Maury and Williamson counties. The Williamson Source and Maury County Source both carried the city's announcement of the contract.
What's next
Construction is set to begin in spring 2027. The city said it will post updates on the project page as work moves along.
Sources
- Spring Hill approves $8.2 million road project at Port Royal, Buckner Lane, Williamson Source
- Port Royal Road - Buckner Lane Intersection, City of Spring Hill
More from Morningline Research
More numbers: Spring Hill, TN building permit activity, updated weekly.
- Spring Hill Approves $12 Million Sewer Line to Columbia to Add Capacity During Its Sewer Moratorium
- Austin's airport gets a $60 million permit for its six-gate Concourse M
- Acutronic Plans 2027 Groundbreaking for Bastrop Jet Engine Factory, Likely Larger Than 20,000 Square Feet
- BGMU Starts Work on $210 Million-Plus Bowling Green Water Recovery Plant Expansion, Largest in Utility's History