The city of Lebanon, Tennessee, is weighing higher utility rates to pay for a new sewer treatment plant, an expanded water pumping facility and other infrastructure, WSMV reported. Much of the cost would fall on new development.
What the rate plan would do
If the proposal is approved:
- customers would pay just under $13 more for every 5,000 gallons of water and sewer use
- gas customers would pay nearly $17 more per month
- new developers would be charged fees more than 60% higher
Not every customer in Lebanon would see the higher rates, because the city provides utilities to only part of the area. A recent study found the rates would still be lower than those of other utilities nearby, WSMV reported. Utility officials said they plan to keep reviewing rates as the area grows to see whether they can come down or need to keep rising.
Get today’s Lebanon report for your trade, free →
Three sites still in the running
The city has not picked a location for the plant. Three sites remain under consideration, WTVF-TV reported:
- Site 7, near Horn Springs Road and Oriole Drive, northwest of Lebanon
- Site 22, a plot near Maple Hill Road
- Site 13A, a combination of lots near South Hartman Drive
Neighbors of Site 7 have hired a lawyer. Their attorney sent a letter to city and county leaders arguing that Lebanon cannot build the plant at that location without county approval, both for zoning and for financing, because the site is outside city limits. The letter asks that the site be dropped.
Neighbor Michael Hershey took those concerns to the Wilson County Commission last week. "They passed a resolution in June unanimously opposing the city in the idea of operating a sewer plant in the county," he said.
The city's case
Lebanon Mayor Rick Bell did not respond to WTVF's request for an interview. In a March interview with the station, Bell stressed the need for the new plant. "If we don't build it, the future of this city will be a failure," he said.
What's next
The rate proposal goes before the Lebanon city council. The site selection for the plant is still open.
Sources
- Utility rate plan would fund sewer plant, water pumping expansion in Lebanon, WSMV
- Neighbors fight Lebanon's proposed sewer site, say city needs county approval to move forward, NewsChannel 5
More from Morningline Research
- Lebanon's New Wastewater Treatment Plant: Four Sites Stay in Play as City Council Waits on Environmental and Cost Studies
- Austin's airport gets a $60 million permit for its six-gate Concourse M
- Acutronic Plans 2027 Groundbreaking for Bastrop Jet Engine Factory, Likely Larger Than 20,000 Square Feet
- BGMU Starts Work on $210 Million-Plus Bowling Green Water Recovery Plant Expansion, Largest in Utility's History