Lebanon Weighs Higher Water, Sewer Rates and Developer Fees to Pay for New Sewer Plant as Site Choice Continues

Lebanon, Tennessee, is weighing utility rate increases and developer fees more than 60% higher to pay for a new sewer treatment plant and expanded water pumping, while neighbors of one of three finalist plant sites in Wilson County argue the city needs county approval to build there.

By Morningline Research · November 23, 2026
Lebanon Weighs Higher Water, Sewer Rates and Developer Fees to Pay for New Sewer Plant as Site Choice Continues
Graphic: Morningline Research

The city of Lebanon, Tennessee, is weighing higher utility rates to pay for a new sewer treatment plant, an expanded water pumping facility and other infrastructure, WSMV reported. Much of the cost would fall on new development.

What the rate plan would do

If the proposal is approved:

Not every customer in Lebanon would see the higher rates, because the city provides utilities to only part of the area. A recent study found the rates would still be lower than those of other utilities nearby, WSMV reported. Utility officials said they plan to keep reviewing rates as the area grows to see whether they can come down or need to keep rising.

Get today’s Lebanon report for your trade, free →

Three sites still in the running

The city has not picked a location for the plant. Three sites remain under consideration, WTVF-TV reported:

Neighbors of Site 7 have hired a lawyer. Their attorney sent a letter to city and county leaders arguing that Lebanon cannot build the plant at that location without county approval, both for zoning and for financing, because the site is outside city limits. The letter asks that the site be dropped.

Neighbor Michael Hershey took those concerns to the Wilson County Commission last week. "They passed a resolution in June unanimously opposing the city in the idea of operating a sewer plant in the county," he said.

The city's case

Lebanon Mayor Rick Bell did not respond to WTVF's request for an interview. In a March interview with the station, Bell stressed the need for the new plant. "If we don't build it, the future of this city will be a failure," he said.

What's next

The rate proposal goes before the Lebanon city council. The site selection for the plant is still open.

Want to wake up knowing what’s being built near you?

Tell us what you do and where, and we’ll send you a free sample report.

Your report comes from dave@morninglineleads.com, so please check your spam or junk folder if you don’t see it. Free, no card, no obligation. We work with one company per trade in each area, so if yours is taken, we’ll let you know.

Sources

More from Morningline Research