Leander ISD trustees in Leander, Texas, approved the maximum guaranteed construction costs for the district's next two elementary schools on Nov. 12, moving both 2023 bond projects into construction, Community Impact reported.
Elementary 31 has an approved construction cost limit of $66.7 million. Elementary 32 has a limit of $62.8 million. The vote was 4-2, with trustees Sade Fashokun and Paul Gauthier against.
Where the schools go
Elementary 31 is proposed near the intersection of FM 2243 and CR 175 in Leander, according to the district's project page. It is meant to add room in the northeast part of the district and relieve the Tarvin, Parkside and Akin feeder area.
Get today’s Leander report for your trade, free →
The district lists the exact Elementary 31 figure at $66,708,477.91, the second guaranteed maximum price (GMP) for the school. An earlier GMP of $2,024,553, approved in 2023, paid for mechanical and electrical equipment and the thin brick veneer cast into the tilt wall panels. To hit an August 2028 opening, the district said construction would begin early in the spring of 2027.
Elementary 32 will be built in the Travisso community. Under a plan presented in October, the Mason Elementary community would move to the new campus. District data cited by Community Impact show only 24% of students zoned to Mason live in its immediate area, while 51% live in the Travisso corridor and another 25% in surrounding areas.
A full meeting
Over 50 community members signed up to speak at the Nov. 12 meeting. Many urged the board to build both campuses as promised in the bond. Others, including Mason parents, said the current Mason campus is a neighborhood school and questioned whether enrollment projections justify a new one.
Chief Operations Officer Jeremy Trimble told the board both projects have already been pushed back. No. 31 first had an opening date of 2025-26, and No. 32 of 2027-28. He said further delays would hurt the district's ability to deliver both within the bond budget.
Fashokun, who voted no, raised concerns about enrollment projections and the risk of underenrolled campuses later on.
What's next
Both schools were approved under Proposition A in the 2023 bond and are now scheduled to open in August 2028. Work on Elementary 31 is set to start next spring.
Sources
- Leander ISD pushes construction on Elementary 31 and 32 forward, Community Impact
- Bond: Elementary School 31, Leander ISD
More from Morningline Research
- Leander Approves Phasing Plan for 188-Lot Oakwood Hills Subdivision off Nameless Road
- Austin's airport gets a $60 million permit for its six-gate Concourse M
- Acutronic Plans 2027 Groundbreaking for Bastrop Jet Engine Factory, Likely Larger Than 20,000 Square Feet
- BGMU Starts Work on $210 Million-Plus Bowling Green Water Recovery Plant Expansion, Largest in Utility's History